2.40 Release Status
This document contains the development status of Openbravo ERP R2.40. You can comment this document posting your comments on the developers forum.
Contents |
ERP Core Projects
| Team | Project | Owner | Iteration | Functional Specification | Technical Documentation | Build | QA Test Plan | QA Test Execution | Bugs | Project Merged to Trunk | Comment |
| Platform | PostgreSQL 8.3 Support | Cromero | 1 | N/A | N/A | Complete | Acceptance test | Complete | 0 | Yes | |
| Platform | Code Cleanup | ALO | 1 | N/A | Complete (Apr 25) | Complete | N/A | Complete | 0 | Yes | |
| Platform | Audit | ALO | 1 | Complete | Complete | Complete | Complete | Complete | 0 | Yes | |
| 2 | N/A | N/A | Complete | N/A | N/A | 0 | Yes |
| |||
| Platform | DB source manager project | AMO | 1 | N/A | Complete | Complete | N/A | N/A | 0 | N/A | |
| Platform | Security review | ALO | 1 | Complete | Complete | Complete | Complete | Complete | 0 | Yes | |
| 2 | NA | NA | Complete | Complete | Complete | 7 | Yes | ||||
| Platform | Keyboard shortcuts and navigation | DBA | 1 | Complete | Complete | Complete | Complete | Complete | 0 | Yes | |
| 2 | N/A | N/A | Complete | Complete | Complete | 17 | Yes | ||||
| Platform | Performance optimization | ALO | 1 | Complete | Complete | Complete | N/A | N/A | 0 | Yes | Project completed through scope reduction. |
| Platform | Heartbeat | TWO | 1 | Complete | Complete | Complete | Completed (Partially) | Completed | 2 | Yes | |
| Platform | Improve UI visibility (feedback on UI status) | DBA | 1 | Complete | Complete | Complete | Complete | Complete | 2 | Yes |
|
| Team | Project | Owner | Iteration | Functional Specification | Technical Documentation | Build | QA Test Plan | QA Test Execution | Bugs | Project Merged to Trunk | Comment |
| Platform | Ajax component in all datagrids | IPE | 1 | Complete | Complete | Complete | Complete | Complete | 3 | Yes | |
| 2 | Complete | Complete | Complete | Complete | Complete | 0 | Yes | ||||
| 3 | Complete | Complete | Complete | Complete | Complete | 0 | Yes | Change all remaining selectors. | |||
| Functional | Goods Receipt by PO number | GDA | 1 | Complete | Missing | Complete | Missing | Complete | 0 | Yes |
|
| Functional | Requisitions | GDA | 1 | Complete | Complete | Complete | Complete | Complete | 0 | Yes | Successfully merged on rev. 3223 |
| Functional | Web services for CCV2 | IPE | 1 | Complete | Complete | Complete | Complete | Complete | 0 | Yes | 80% of Test execution completed (blocked for bug fixes) - Remaining testcases will be tested on alpha release. |
| Functional | Web services for POS | Adrián | 1 | Complete | Complete | Complete | Complete | Complete | 0 | Yes | Two separate tests: OpenbravoERP side completed (included in CCV2 project) and OpenbravoPOS test (not started) |
| Localization | Multi-schema | EAR | 1 | N/A | N/A | Complete | Complete | Complete | 4 | Yes | |
| Localization | Payment aging balance | Alsasua | 1 | Complete | Complete | Complete | N/A | Complete | 0 | Yes | |
| Localization | BP multiple selector in payment report | Alsasua | 1 | Complete | Complete | Complete | N/A | N/A | 0 | Yes | |
| Localization | Budget report | Alsasua | 1 | Complete | Complete | Complete | N/A | Complete | 0 | Yes | |
| 2 | Complete | Complete | Complete | N/A | Complete | Yes | |||||
| Team | Project | Owner | Iteration | Functional Specification | Technical Documentation | Build | QA Test Plan | QA Test Execution | Bugs | Project Merged to Trunk | Comment |
| Localization | International bank account numbers | Alsasua | 1 | Complete | Complete | Complete | Complete | Complete | 1 | Yes | |
| Localization | Security of permanent closing | Alsasua | 1 | N/A | N/A | Complete | Missing | Complete | 0 | N/A | |
| Community | Withholding tax | EAR | 1 | Complete | N/A | Complete | Complete | Complete | 0 | Yes | |
| Community | VAT Register | EAR | 1 | Complete | N/A | Complete | Complete | Complete | 0 | Yes | |
| Community | Pareto report | Cromero | 1 | Complete | Complete | Complete | N/A | Complete | 0 | Yes | |
| Community | Salary Category Historic | Cromero | 1 | Complete | Missing | Complete | Complete | Complete | 0 | Yes | |
| Release Management | Improved installer | Jpabloae | 1 | Complete | Complete | Complete | Complete | Complete | 0 | N/A | |
| Team | Project | Owner | Iteration | Functional Specification | Technical Documentation | Build | QA Test Plan | QA Test Execution | Bugs | Project Merged to Trunk | Comment |
| Functional | Projects & Service Review | Rafaroda | 1 | Complete | N/A | Complete | Complete | Complete | 0 | Yes | |
| Functional | Table Access Level Review | PMA | 1 | Complete | N/A | Complete | N/A | Complete | 0 | Yes | |
| Functional | Consume Initial Focus Position | PMA | 1 | Complete | N/A | Complete | N/A | Complete | 0 | Yes |
External Projects
The following projects enhance the overall Openbravo system are not strictly part of the ERP core as they are distributed as tools around it.
| Team | Project | Owner | Iteration | Functional Specification | Technical Documentation | Build | QA Test Plan | QA Test Execution | Bugs | Project Merged to Trunk | Comment |
| Community | Integration with BI server | External | 1 | Complete | Complete | Complete | Not started (May 16) | Not started (May 16) | 0 | N/A | This project is an external add on that does not impact Openbravo 2.40, it is still possible to complete it in the 2.40 time frame without impacting 2.40. |
| Localization | PO import/export (translation) | Alsasua | 1 | Complete | N/A | In progress | Not started | Not started | 0 | N/A | External project not impacting Openbravo core |
Legend:
- Not started: activity not yet started
- In progress: activity in progress
- Missing: activity is complete; deliverable was not produced
- Complete: activity is complete; deliverable is available
- N/A: activity is not applicable for this project
Collaterals
The following is a list of tasks that need to be executed to develop all the required collaterals before production.
| Collateral | Task | Owner | Status | Comment |
| ER Diagrams | Update to 2.40 | IPE | Done (Jun 19) | |
| User's Guide | Update screen shots | PLU | In progress (est. Jun 20) | 4 out of 11 pages updated |
| Update User Interface section | DBA | Done (Jun-4) | ||
| Update Windows documentation to account for ability to configure initial focus position | DBA | Done (May-27) | ||
| Update Procurement documentation to integrate requisitions | GDA | Done (June-12) | ||
| Update Goods Receipt documentation to integrate ability to receive by PO number | GDA | Done (May-26) | ||
| Update Warehouse Management Analysis Tools documentation to add Pareto Report | CRO | Done (May-27) | ||
| Update Projects & Service Management documentation | RRO | Done (Jun-4) | Waiting for screen shots update. | |
| Integrate Withholding Tax and VAT Register in Financial Management documentation | EAR | Done (Jun-19) | ||
| Integrate International Bank Accounts features in Bank Setup and Business Partner setup documentation | DAL | Done | ||
| Document Budget Report in [[
User_Manual_2.40/Financial_Management#Budget |Financial Management Analysis Tool]] documentation | DAL | Done | ||
| Document Historic Salary Category in Master Data Management documentation | CRO | Done (May-27) | ||
| Add Heart Beat Documentation | TWO | Done (June-09) | ||
| Installation Guide | Update | JAR | Done (May-23) | |
| Upgrader | Upgrader to 2.40 | JAR | In progress (Jun-20) | |
| Functional Documentation | Update Accounting Documentation to take into consideration Multiple Accounting Schemas | EAR | Done (Jun-19) |
|
| Web services documentation | Update documentation of web services objects and methods | IPE | Done (Jun-16) |
Summary
You can track our progress at Summary Historical Status.
Bug Fixing
Also Openbravo is doing a big effort in order to improve our quality and what better than fixing bugs. Openbravo aims to reduce drastically the number of opened bugs in 2.40 release. You can see our expectations and the real evolution here: Openbravo ERP bugs evolution