2.50 Release Status

This document contains the development status of Openbravo ERP R2.50. You can comment this document posting your comments on the developers forum.

ERP Core Projects

Project FR Class Owner Iteration Functional Specification Technical Documentation Build QA Test Plan QA Test Execution Bugs Project Merged to Trunk Comment
UUID 4109 ***** alostale 1 Complete Complete Complete

Estimated compl. date: 21 jul

Not started. To be finished on August 6th Not started. To be finished on August 8th 0 Yes (r2.50 branch)
Modularity 126 ***** iciordia 1 In progress. To be finished on July 31th Not started. To be finished on August 14th Not started. To be finished on September 30th Not started. To be finished on August 4th Not started. To be finished on August 18th 0 No Func spec 1st aug
Reference data management 503 ***** iciordia 1 In progress. To be finished on July 31th Not started. To be finished on August 14th Not started. To be finished on September 30th Not started. To be finished on August 4th Not started. To be finished on August 18th 0 No This project is part of modularity
Industry templates 4160 ***** iciordia 1 In progress. To be finished on July 31th Not started. To be finished on August 14th Not started. To be finished on September 30th Not started. To be finished on August 18th Not started. To be finished on August 25th 0 No This project is part of modularity
Installing Openbravo in an existing schema 4079 **** jpabloae 1 Not started Not started August 1st Not started. To be finished on August 18th Not started. To be finished on August 25th 0 No
Upgrade to the latest version of Dojo 4141 **** dbaz 1 Complete Complete In progress. To be finished on September 12th Not started. To be finished on August 25th Not started. To be finished on September 1st 0 No
Make interface components HTML standard 421 **** dbaz 1 Complete NA. At the end of the project a list with the changes will be included Not started. To be finished on October 31th Not started. To be finished on August 25th Not started. To be finished on September 1st 0 No
Support the latest version of iReport (iReport 2.0.5 does not work). See library auditing project. 417 **** jordimash 1 NA In progress. To be finished on August 15th In progress. To be finished on August 15th Not started. To be finished on August 25th Not started. To be finished on August 31st 0 No
Update all external libraries to latest version. See library auditing project. 4162 **** jordimash 1 NA In progress. To be finished on August 15th In progress. To be finished on August 15th Not started. To be finished on August 25th Not started. To be finished on August 31st 0 No
Allow comma ',' as decimal separator for numbers 3996 **** dbaz 1 Complete Complete Not started. To be finished on October 31th Not started. To be finished on September 8th Not started. To be finished on September 15th 0 No
Functions and variables in Javascript have Spanish names 4077 **** dbaz 1 Complete NA. At the end of the project a list with the renamed functions will be included In Progress: To be finished on August 29th NA NA 0 No
Unicode fonts in iReports 4139 **** pheenan 1 NA Not Started - Target Date August 22nd Not Started - Target Date September 12th Not Started - Target Date September 1st Not started - Target Date September 22th 0 No
Remove unused AD elements 4116 **** pheenan 1 Complete Not Started - Target Date August 22nd Not Started - Target Date September 12th NA NA 0 No
Eliminate Frames 4129 **** dbaz 1 Complete NA In progress. To be finished on August 22th Not started. To be finished on September 22nd Not started. To be finished on September 29th 0 No
Review all the .xsql that has insert or update statements 583 **** rafaroda 1 NA Complete Not started: To be finished on September 12th Not started. To be finished on September 22nd Not started. To be finished on September 29th 0 No
Centralized control changes 422 **** iperdomo 1 Complete In progress (31th Jul) Not started (15th Aug) Not started. To be finished on September 29th Not started. To be finished on October 6th 0 No
WAD hints generation 3304 **** alostale 1 Complete Complete Not started NA NA 0 No
Accounting report review 4110 *** Alsasua 1 Not started (Aug 21st) NA Not started (Aug 29th) Not started. To be finished on Octuber 6th Not started. To be finished on October 13th 0 No
Currency in reports - non accounting reports 2181 *** rafaroda 1 Complete Complete Not started: To be finished on September 12th Not started. To be finished on Octuber 13th Not started. To be finished on October 20th 0 No Technical Documentation is missing from 2 examples that will be added once the built is started.
Create Element Value Operands as part of Initial Client Setup 2997 *** Alsasua 1 NA NA Complete Not started. To be finished on Octuber 20th Not started. To be finished on October 27th 0 No
Label clean up 504 *** pheenan 1 Complete Not Started - Target Date August 18th Not Started - Target Date September 12th Not Started - Target Date August 22nd Not started - Target Date November 3rd 0 No
Goods Movement Report 243 *** pheenan 1 Complete Not Started - Target Date August 22nd Not Started - Target Date September 30th Not started - Target Date September 30th Not started - Target Date November 10th 0 No
Project scheduling capabilities enhancement 4563 *** rafaroda 1 Complete Complete Not started: To be finished on August 22th Not started. Not started. 0 No
Project Evolution report 4505 *** rafaroda 1 Complete Complete Not started: To be finished on August 29th Not started. Not started. 0 No


Material Transaction Report does not have clear labeling for shipments versus receipts 550 *** rafaroda 1 Complete NA Not started: To be finished on September 26th Not started Not started 0 No
Feedback when de-activating Taxes and Price Lists 452 *** rafaroda 1 Complete Complete Not started: To be finished on September 26th Not started. To be finished on November 12th Not started. To be finished on November 15th 0 No
Complete and process imported orders 4322 *** rafaroda 1 Complete Complete Not started: To be finished on September 26th Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Properly handling the posting of inactive documents 2579 *** eargal 1 NA NA Not started (Oct 7th) Not started. To be finished on November 18th Not started. To be finished on November 22nd 0 No
Removing accounting from orders 4281 *** Alsasua 1 Not started (Sept 18th) Not started (Sept 23th) Not started (Sept 30th) Not started. To be finished on November 24th Not started. To be finished on November 28th 0 No
Close and opening entry navigation 4282 *** eargal 1 Not started (Oct 9th) Not started (Oct 13th) Not started (Oct 17th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Remove the paid flag from payment 4285 *** iperdomo 1 NA NA Complete Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Replace internal account with in-transit account 4286 *** eargal 1 NA NA Complete Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Add organization filter to the accounting create and delete process 4287 *** eargal 1 Not started (Oct 20th) Not started (Oct 21st) Not started (Oct 27th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Display account value (number) in account tree 4290 *** ggil 1 Complete Complete Complete Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Tax Report: print provider invoice number 4269 *** Alsasua 1 NA NA Not started (Oct 1st) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Enhanced Multi-organization Support 4144 ** nserrano 1 Complete Not started. To be finished on September 16th (tbd 5d) Not started. To be finished on October 20th (tbd 15d) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Movable columns in a grid 4142 ** dbaz 1 Complete NA Not started. To be finished on December 12th Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Save grid layout 4143 ** dbaz 1 Complete Not started. To be finished on December 12th Not started. To be finished on December 12th Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Editable multi-record grid widget 3059 ** dbaz 1 Complete Not started. To be finished on April 24th 2009 Not started. To be finished on April 24th 2009 Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Background process management 4147 ** awolski 1 In Progress. Target 22nd August In Progress. Target 22nd August Started. Target October 30th. Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No Project being completed in iterations. Documentation evolving.
Sales dashboard 4167 ** pmagnin 1 In progress. Target Sept 8th Not started. Target Sept 15th Not started. Target Oct 15th Not started. Target Oct 31th Not started. Target Oct 31th 0 No
Translation management 4058 ** pheenan 1 Complete In progress - Target Date August 22nd Not started - (High Priority) 30 Sep 2008 Not started - Target Date 30 Sep 2008 Not started - Target 30 Sep 2008 0 No User stories - 1,2,4,5,8,14
2 NA Not Started - Target Date August 22nd Not started - (Med Priority) 31 Oct 2008 Not Started - Target Date 31 Oct 2008 Not Started - Target 31 Oct 2008 0 No User stories - 3,6,12,13,17,19
3 NA Not Started - Target Date August 22nd Not started - (Low Priority) Not Started Not Started 0 No User stories - 7,9,10,11,15,16,18,20,21,22,23 - This iteration will not be completed for 2.50 release due to dependencies.
Complete Spanish Localization Pack 4119 ** Alsasua 1 Not started (Oct 16th) Not started (Oct 20th) Not started (Oct 24th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No


Cash Flow Statement - Indirect Method 4270 ** eargal 1 Not started (Sep 16th) Not started (Sep 19th) Not started (Sep 26th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
UOM management: extend model like OB v.1 3019 ** gorkaion 1 In progress Target date August 13th Not started (September 9th) Not started (September 30th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No Pending to define the list of windows, reports and processes that need modification
Improve standard report for printed documents 4118 ** cromero 1 Not started Not started September 30th Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Simple production accounting 4169 ** eargal 1 Complete NA Complete Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Alert icon should change dynamically 4170 ** dbaz 1 Complete Complete Complete Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Show attachment status with icon 4171 ** dbaz 1 Complete Complete Complete Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Warehouse picking 4174 ** gorkaion 1 In Progress (August 13th) Not started (September 9th) Not started (September 30th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No Pending review of existing reports


Modify Create Lines From * cromero 1 Complete Complete Complete Not started. Not started. 0 No


Advance Payment * cromero 1 Complete N/A Pending to integrate. Planned date 1st September Not started. Not started. 0 No
A help message (info type) UI pattern 495 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No To be done together with "WAD hints generation"

There are some open questions pending before starting with the implementation.

Single record window UI pattern 4113 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Implement Image reference in dictionary 3182 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Sortable drop down list 4200 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Select and process UI pattern 4196 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Report UI pattern in Application Dictionary 4194 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Direct link navigation: select tab to navigate to 4017 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No There are some technical issues to be discussed before starting with its implementation.
LiveSearch on selectors 3379 * iperdomo 1 Not started. To be finished on August 8th Not started. To be finished on August 14th Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Selector UI pattern in Application Dictionary 4191 * iperdomo 1 Not started. To be finished on August 8th Not started. To be finished on August 14th Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No To be done together with "LiveSearch on selectors"
Intrusive alerts 4172 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Price including taxes 4175 * cromero 1 Not started Not started September 15th Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Integration with on line calendar 4176 * iperdomo 1 Complete Not started Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Product attributes revision 4149 * gorkaion 1 Completed Pending QA review (July 25th) Not started (October 17th) Not started (October 30th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Reservations for work orders and sales orders 4229 * gorkaion 1 Not started (September 26th) Not started (October 1st) Not started (October 10th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No This project depends on UOM Management, Warehouse Packing and Work Requirement Status
Manufacture to order 4230 * gorkaion 1 Not started (August 25th) Not started (October 10th) Not started (October 17th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Work requirement status 3268 * gorkaion 1 Not started (September 19th) Not started (September 23th) Not started (October 7st) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
User password management 500 * alostale 1 Complete Complete Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
e-commerce Integration 3155 * jordimash 1 In progress. To be finished on the 31st of August. In progress. To be finished on the 31st of August. Not started. To be finished on the 30st of September. Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Data access layer 501 * iperdomo 1 Complete Complete Started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
CRUD web services at relational table level 4177 * iperdomo 1 Not started Not started Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Business events at relational table level 4192 * iperdomo 1 Not started Not started Not started Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No


Business services 4193 * awolski 1 Not started. Target 1st August Not started. Target 1st August Not started (October 30th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Financial Management flow review 528 * eargal 1 In progress (August 8th) Not started (August 15th) Not started (tbd 20d August 26th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Eliminating account combination concept 4266 * eargal 1 Not started (Sep 2nd) Not started (Sep 5th) Not started (Sep 12th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Rules driven accounting engine 4267 * nserrano 1 In progress. To be finished on September 15th Not started. To be finished on September 29th Not started. To be finished on October 30th (20d tbd) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Easy accounting entry window 4268 * eargal 1 Not started. To be finished on Sep 30th Not started. To be finished on (Oct 13th - Alsasua) Not started. To be finished on Nov 4th (tbd 20d) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Bank statement reconciliation process review 3999 * eargal 1 Not started (Aug 1st Draft 14th) complete Not started (Aug 15th) Not started (tbd 10d Sep 15th) Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No
Right to left support 4402 * Alsasua 1 Not started. (August 15th) NA NA Not started. To be finished on December 1st Not started. To be finished on December 1st 0 No


Project Type and Project Category enhancements 4562 * rafaroda 1 Not Started: To be finished on August 29th Not Started: To be finished on August 29th Not started: To be finished on October 10th Not started. Not started. 0 No
Project filter in 'Create AP Expenses Invoices' and 'Create Sales Orders from Expenses' processes 402 * rafaroda 1 Not Started: To be finished on August 29th Not Started: To be finished on August 29th Not started: To be finished on October 10th Not started. Not started. 0 No

Legend

Description of the non self-explaining columns:

Status of the activities:

Summary

You can track our progress at Historical Status.